The construction’s almost complete
Your road trips from Dubai to Hatta and surrounding areas are about to get much easier.
According to Dubai’s Roads and Transport Authority (RTA, seventy-two per cent of the construction work on a road link, spanning 38 km in total, for Dubai’s Margham, Lehbab, Al Lisaili and Hatta has been completed.
The project includes 19 km of roadwork and the addition of lighting poles along another 19 km of existing streets.
The internal roads project at Margham covers the construction of roads extending 5 km along Dubai-Al Ain Road, near Skydive Dubai. According to the authorities, the project will benefit more than 11,000 residents.
At Lehbab, the project will include paving roads extending 5 km along with infrastructure works of rainwater drainage and streetlights.
You might also like: ‘Tarahum for Gaza’ events in Dubai
The road works span 7 km at Al Lesaili and includes street lighting works for the existing roads at Saih Assalam near the Last Exit and Al Qudra Lakes over 14 km.
And finally at Hatta, the project covers the construction of roads extending 2 km at Saa’eer, Al Salami, and Suhaila.
RTA has recently completed the construction of internal roads within three residential districts, namely Al Quoz 2, Nad Al Sheba 2, and Al Barsha South 3, extending 37 km in total and inhabited by 12,000 persons.